Question: Question 1: 50/50 Rule Based on the above Gantt chart, the data given below, and by using the 50/50 rule - complete the Earned Value

Task A Week 1 Week 2 Week 3 Week 4 Task B

Question 1: 50/50 Rule

Based on the above Gantt chart, the data given below, and by using the 50/50 rule - complete the Earned Value table for tasks A, C, F, J, K M and O. Task D Task C Task F Task G Task J Task E

Question 2: Calculate Earned Value Indicators

Based on the following data:

The Budget At Completion (BAC) cost of the project is estimated to be: $52,250.

  • Earned value data is available for the first three weeks of the project (see below).
  • The project is due to end on week four (4)
Task H Task I Task K Task L Task M Task N

Based on the above data, calculate the following earned value indicators:

Task O Legend: Planned Task Task has been completed (as of week

Question 3: Earned Value Management Dashboard

3) Tasks whose planned status does not its match actual status Tasks

Question 4: Interpret the Projects Status

  1. What is the current week three (3) status of the project?
    • Is the project on schedule, behind schedule or ahead of schedule?
    • Is the project on budget, under budget or over budget?
  2. If progress continues at its current rate how much will the project likely cost?
    • Ensure that you reference the earned value terms and findings in your answer.

Legend: Planned Task Task has been completed (as of week 3) Tasks whose planned status does not its match actual status Tasks actual status New projected completion 

Task A Week 1 Week 2 Week 3 Week 4 Task B Task D Task C Task F Task G Task J Task E Task H Task I Task K Task L Task M Task N Task O Legend: Planned Task Task has been completed (as of week 3) Tasks whose planned status does not its match actual status Tasks actual status New projected completion

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To answer the questions lets break it down step by step Question 1 5050 Rule The 5050 rule states that 50 of the value is earned when a task starts an... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!