Question: Leila is estimating a task duration and she has got an optimistic duration of 18 days, a pessimistic duration of 36 days, and a most

Leila is estimating a task duration and she has got an optimistic duration of 18 days, a pessimistic duration of 36 days, and a most likely duration of 24 days. What is the standard deviation of the e