Question: Les is concerned that his variable cost per unit projection for a project may not be reliable. Which type of analysis will help him determine
Les is concerned that his variable cost per unit projection for a project may not be reliable. Which type of analysis will help him determine the effect that an incorrect variable cost estimate will have on the final outcome of the project?
| a | Monte Carlo simulation |
| b | Financial break-even analysis |
| c | Sensitivity analysis |
| d | Contribution margin analysis |
| e | Scenario analysis |