Question: Min is concerned that her variable cost per unit projection for a project may not be reliable. Which type of analysis will best help her
Min is concerned that her variable cost per unit projection for a project may not be reliable. Which type of analysis will best help her determine the effect that an incorrect variable cost estimate could have on the final outcome of the project?
Net income break-even analysis
Financial break-even analysis
Sensitivity analysis
Contribution margin analysis
Scenario analysis