Question: Let us consider again the equipment rental process. This time we take the perspective of the site engineer, whose goal is to have the required
Let us consider again the equipment rental process. This time we take the perspective of the site engineer, whose goal is to have the required equipment available on site when needed. From this perspective, the main issue is that in about 10 % of cases, the requested equipment is not available on site the day when it is required. When this happens, the site engineer contacts the suppliers directly to resolve the issue, but still, resolving the issue may take several days. It is estimated that each such delay costs $400 per day to BuildIT. By inspecting a random sample of delayed equipment deliveries during a one - year period and investigating the cause of each occurrence, an analyst found that:
21 occurrences were due to the approval process taking too long (more than a day) due to mistakes or misunderstandings. For these cases, the delay was one day on average.
Question- Use information above to answer below
What is the cost for the approval delay in the sample? (select 1)
A-8400
B-8800
C-9000
D-9500