Question: Let's say you are looking to calculate the Earned Value for a project that has a Project Plan that looks something like this: (a) Budget

Let's say you are looking to calculate the Earned

Let's say you are looking to calculate the Earned Value for a project that has a Project Plan that looks something like this: (a) Budget = 50,000,000 (b) Activities = 20 (equally weighted) (c) Duration = 10 months And for simplicity we'll assume the project spend rate is the same each month until completion. At month 5 your personnel in the field are reporting that you are 40% complete on the project and you've spent 30,000,000. What does your Earned Value look like

Step by Step Solution