Question: Lets start with a basica slightly modified version of a midterm question: Draw an activity-on-node network diagram for the following project, including the estimated time
Lets start with a basica slightly modified version of a midterm question: Draw an activity-on-node network diagram for the following project, including the estimated time for each activity:
| Activity | Optimistic Time (weeks) | Most likely weeks | Pessimistic Time weeks | Prdecessor time weeks |
| A | 2 | 3 | 4 | - |
| B | 4 | 5 | 12 | - |
| C | 4 | 6 | 8 | A,B |
| D | 3 | 7 | 11 | C |
| E | 7 | 9 | 14 | D |
| F | 1 | 2 | 3 | C |
| G | 9 | 11 | 13 | F |
| H | 4 | 8 | 12 | C |
| I | 2 | 6 | 16 | G,H |
| b) What is the critical path, expected duration, and variance of the project? |
| c) Using the expected times you calculated, which activities have slack and how much? |
| d) What are the chances that you can finish this project in 34 days? |
| e) If I gave you an extra resources (say 5 person-weeks of work) what would you do |
| with them? |