Question: Lets use a simple example and move it away from the business world for now. You discover you are having guests coming in from out
Lets use a simple example and move it away from the business world for now.
You discover you are having guests coming in from out of town next week, but
you are going to be out of town on business this week and the house needs
some attention. You do some
quick calling around to cleaning
services and find Sarah, who will
come out for $20 an hour. You
engage her for a 40-hour week.
You budget that you can afford $800 for this cleanup.
Since youre a project manager, you quickly prepare a list
of 40 one-hour tasks for her and leave them on the counter
as prearranged. However, when you arrive home after
your trip, your list of tasks has checkmarks of completion
by only some of the items.
Answer thef ollowing:
Budget at Completion
PV: Planned Value
EV: Earned Value
SPI: Schedule Performance Index
SV: Schedule Variance
AC: Actual Cost
CPI: Cost Performance Index
CV: Cost Variance
EAC: Estimate at Completion
Note:
Sarah was sick with the flu, so I' m her brother, Mike, and I came instead to help her out. She didn't want to let you down. Sorry, but I only got 32 of your tasks done. I m taking the $800 check to Sarah.
Please feel free call me again