Question: Level the resources for a project with the workload diagram subsequently. In the time-phased diagram at the top of the figure, dotted lines indicate slack.

Level the resources for a project with the

Level the resources for a project with the workload diagram subsequently. In the time-phased diagram at the top of the figure, dotted lines indicate slack. 8 Discuss pros and cons of the alternatives available. D E H 1 J A G B F 15 G Number of workers 10 F 5 D B J E A H 2 4 8 10 6 Weeks