LF 1. The table below is a segment of network analysis of a project of both the forward and backward pass but with some missing entries. The network continues after tasks W and the LF assigned there comes from the hard due date. Task Predecessors ES EF LS R . 44 49 S R 49 52 60 T R 49 54 60 U ST 60 V U 68 W V 78 84 What is the slack of activity S? 60