Question: Question: solve by project management Complete the oppiste table. Develop the AON network diagrams for the project. Use Forward and Backward Pass calculations to Fill
Question:
solve by project management
Complete the oppiste table.
Develop the AON network diagrams for the project.
Use Forward and Backward Pass calculations to Fill
table
Draw Gantt chart of the ES schedule and show the
activity slack in the chart.
What is the project completion time?
Highlight the critical path in the network.
If the indirect costs for each project duration are
$ time units $ $ and
$ complete Table
Plot the total direct, indirect, and project costs for
each of these durations on a costtime graph?
What is the optimum costtime schedule for the
project? What is this cost?
Table : Project costs by duration
Answer:
Table : Earliest and Latest Schedule and slack time
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock