Question: Question: solve by project management Complete the oppiste table. Develop the AON network diagrams for the project. Use Forward and Backward Pass calculations to Fill

Question:
solve by project management
Complete the oppiste table.
Develop the AON network diagrams for the project.
Use Forward and Backward Pass calculations to Fill
table 1.
Draw Gantt chart of the ES schedule and show the
activity slack in the chart.
What is the project completion time?
Highlight the critical path in the network.
If the indirect costs for each project duration are
$400(19 time units), $350(18), $300(17), and
$250(16), complete Table 2.
Plot the total direct, indirect, and project costs for
each of these durations on a cost-time graph?
What is the optimum cost-time schedule for the
project? What is this cost?
Table 2: Project costs by duration
Answer:
Table 1: Earliest and Latest Schedule and slack time
 Question: solve by project management Complete the oppiste table. Develop the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!