Question: LF Slack Q4. (10 Pts. Use the Critical Path Method to solve this problem. Task Immediate Time ES EFLS Predecessors (weeks) A 6 | 5

LF Slack Q4. (10 Pts. Use the Critical Path

LF Slack Q4. (10 Pts. Use the Critical Path Method to solve this problem. Task Immediate Time ES EFLS Predecessors (weeks) A 6 | 5 D 5 EBD L 3 F C E.F 4 a. Construct a CPM network for this project. b. Identify the critical path for this project. What is the total completion time for this project? c. Compute the ES, EF, LS, LF, and slack times for each activity. d. Suppose activity D could be shortened by two weeks. What effect would this have on the completion date? Does the Critical Path change