Question: Li is under contract to manage the Control Schedule process for a road resurfacing project. It will be a very long project, and will involve
Li is under contract to manage the Control Schedule process for a road resurfacing project. It will be a very long project, and will involve subcontractors who will provide materials and resources. Which of the following is most likely NOT part of Li's responsibility to the project?
Select one:
a Team performance assessments
b Risk register update
c Change requests
d Schedule management plan updates