Question: Li is under contract to manage the Control Schedule process for a road resurfacing project. It will be a very long project, and will involve

Li is under contract to manage the Control Schedule process for a road resurfacing project. It will be a very long project, and will involve 35 subcontractors who will provide materials and resources. Which of the following is most likely NOT part of Li's responsibility to the project?
Select one:
a. Team performance assessments
b. Risk register update
c. Change requests
d. Schedule management plan updates