Question: Li is under contract to manage the Control Schedule process for a road resurfacing project. It will be a very long project, and will involve


Li is under contract to manage the Control Schedule process for a road resurfacing project. It will be a very long project, and will involve 35 subcontractors who will provide materials and resources. Which of the following is most likely NOT part of Li's responsibility to the project? Select one: a. Team performance assessments b. Schedule management plan updates c. Change requests d. Risk register update You and your project management team are conducting a two-day workshop to generate and finalize the project schedule. Which of the following pieces of information will NOT help you develop the project schedule? Select one: a. Schedule baseline b. Resource calendars c. Project scope statement d. Activity list