Question: Liabil Activity Time (weeks) Time (weeks) Numal Cost WIII A 4 3 $2,100 Crashing Immediate Predecessor(s) $2,750 BCDEFG 2 1 $2,300 $3,100 3 3
Liabil Activity Time (weeks) Time (weeks) Numal Cost WIII A 4 3 $2,100 Crashing Immediate Predecessor(s) $2,750 BCDEFG 2 1 $2,300 $3,100 3 3 $600 $600 8 4 $2,500 $2,820 A 6 3 $900 $1,350 B 3 2 $3,000 $4,400 C 4 2 $1,400 $1,900 D, E a) Based on the given information regarding the activities for the project, the project length = 16 weeks b) The total cost required for completing this project on normal time = $ 12800 c) For reducing the duration of the project by one week, the activity that should be crashed first is activity D The cost of the project based on the first activity selected for crashing will increase by $ 80 d) The maximum weeks by which the project can be reduced by crashing = 7 weeks. Total cost of crashing the project to minimum (or maximum weeks possible) = A Clear all