Question: Lida is developing an RFP for her project; she is aware that her project organization will have to advance funds to the selected seller, because
Lida is developing an RFP for her project; she is aware that her project organization will have to advance funds to the selected seller, because her technical team has advised that there will likely be a long lead time between the time that the seller orders the materials needed to fulfill the contract and when those materials are received. What type of bonding arrangement should Lida include in the RFP