Question: Line balancing question ( Industrial and system engineering ) : Operation A 1 . 9 min, operation B , 1 . 1 min, expect 7

Line balancing question (Industrial and system engineering):
Operation A 1.9 min, operation B,1.1 min, expect 720 units of products/ day. 8 hours working period/ day.
1. Max output in a day with 1 operator per operation?
2. How many operators to assign to Operation A and Operation B?
3. How many complete units could be
completed with updated staffing?