Question: Line Balancing (Single-Model Lines) 15.12 Show that the two statements of the objective function in single-model line balancing in Equation (15.20) are equivalent. 15.13 The

Line Balancing (Single-Model Lines) 15.12 Show that the two statements of the objective function in single-model line balancing in Equation (15.20) are equivalent. 15.13 The table below defines the precedence relationships and element times for a new model toy. (a) Construct the precedence diagram for this job. (b) If the ideal cycle time =1.1min. repositioning time =0.1min, and uptime propotion is assumed to be 1.0, what is the theoretical minimum number of workstations required to minimize the balance delay under the assumption that there will be one worker per station? (c) Use the largest candidate rule to assign work elements to stations. (d) Compute the balance delay for your solution