Question: Linear Program Identify which, if any, activities should be crashed and how much that would cost her to get everything completed within 8-week timeframe. Remember,

  1. Linear Program Identify which, if any, activities should be crashed and how much that would cost her to get everything completed within 8-week timeframe. Remember, since He is paying personally for the extra crashing time, she wants to minimize costs.
Linear Program Identify which, if any, activities should be crashed and howmuch that would cost her to get everything completed within 8-week timeframe.

Normal time Normal Crash Crash Weeks Saved Crash Costperweek Immediate (weeks) Cost ($) Time (Weeks) Cost ($) Ti - Ti' ( ci' - ci )/Mi Activity Description Predecessor Ti Ci Ti ci' = Mi (Weeks) = Ki ($) A Deciding Dates and Nu 0.5 750 0.25 1,000 0.3 1,000 B Determining Venue 1 250 0.5 750 0.5 1,000 C Sending Out A, B 1.5 750 1 1,250 0.5 1,000 D Inviting Special C 0.5 750 0.25 1,200 0.25 1, 800 E Responding to C 3 500 2 1,500 1 1,000 F Organizing Sessions C 1.5 1,000 1 1,500 0.5 1,000 G Getting registration D, E, F 2.5 500 2 1,000 0.5 1,000 H Last Minute Edits G 1 500 0.5 1,000 0.5 1,000 S 5,000 9,200\f

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!