Question: Lisa Corp, needs to determine the variable utilities rate per machine hour in order to estimate cost for August. Relevant information is as follows. Month
Lisa Corp, needs to determine the variable utilities rate per machine hour in order to estimate cost for August. Relevant information is as follows. Month Machine Hours Worked Utilities Cost April 4,500 $9,060 May 4.200 9,440 June 6,500 10.725 July 7,000 11.400 Lisa anticipates using 8.000 hours of machine time in August. The company uses the high-low method to analyze costs. Required: A. Calculate the variable component of the utilities cost. B. Calculate the fixed component of the utilities cost C. Using the data calculated above, estimate the utilities cost for August.. HTML Editore BIVANI EXXX.EE V GODT 1: 12pt Paragraph MacBook Air 0 888 DIL 55 F7 F