Question: LO 2.2- Consider four processes A,B,C, and D with the burst times 3,3,11,4, respectively. All the processes arrived at time 0. 1. What is the
LO 2.2- Consider four processes A,B,C, and D with the burst times 3,3,11,4, respectively. All the processes arrived at time 0. 1. What is the average turnaround time using FCFS scheduler? 2. What is the average waiting time using FCFS scheduler? 3. When does the RR scheduler perform the same on the above process? For tha towhar nraee Al T+F1n (PClne Al T+FN+F10 (MaCl