Question: LO 7 - 2 1 . The batch size is cut in half on a resource that has a setup time. What is the likely
LO
The batch size is cut in half on a resource that has a setup time. What is the likely impact on the resources capacity?
a Decrease by more than percent
b Decrease by percent
c Decrease by less than percent
e No impact