Question: The batch size is cut in half on a resource that has a setup time. What is the likely impact on the resources capacity? a.

The batch size is cut in half on a resource that has a setup time. What is the likely impact on the resource’s capacity?

a. Decrease by more than 50 percent. 

b. Decrease by 50 percent. 

c. Decrease by less than 50 percent. 

d. No impact.

Step by Step Solution

3.33 Rating (150 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

c Decrease by less than 50 ... View full answer