Question: Loans are evaluated in a process with two resources, The processing time for resource A is 1 1 minutes and for resource B is 6

Loans are evaluated in a process with two resources, The processing time for
resource A is 11 minutes and for resource B is 6 minutes. Demand occurs at the rate
of 2 loan per minute.
What is the implied utilization of resource B?
2200%
1800%
1600%
1200%