Question: Loans are evaluated in a process with two resources the processing time of the first resource is 13 minutes the processing time of the second
Loans are evaluated in a process with two resources the processing time of the first resource is 13 minutes the processing time of the second resource is 45 minutes the first resource has 2 workers and the second resource has 8 workers assume 4 workers are added to the bottleneck resource.
What would be the capacity of this process loans per hour ?
(round your answer to three decimal places)
your help would be appreciated
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
