Question: Logan, a BSI summer intern, has been assigned to handle a new project that the firm has received. This project involves a lot of scheduling
Logan, a BSI summer intern, has been assigned to handle a new project that the firm has received. This project involves a lot of scheduling that has to be handled by Logan. Logan estimates that the first task of the project could be completed in as few as days or could take as many as days, but most likely will require days. What is the day estimate called and how much time should Logan actually assign to the task?
Group of answer choices
probablecase estimate P; days
worstcase estimate W; days
bestcase estimate B; days
None of these are correct
probablecase estimate P; days