Question: Looking for the correct answer here What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? IMMEDIATE PREDECESSOR(S) ACTIVITY

Looking for the correct answer here

Looking for the correct answer here What is the

What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? IMMEDIATE PREDECESSOR(S) ACTIVITY Design (A) Wiring (B) Chip install (C) Software (D) Testing (E) NORMAL CRASH TIME TIME (DAYS) (DAYS) 7 6 9 7 5 4 6 4 9 6 NORMAL COST 800 200 400 800 900 CRASH COST 850 250 450 1,050 1,350 A, B The minimum cost of crashing the following project at Sawaya Robotics by. 4 days is $ 650 (enter your response as a whole number)