Question: LS and LF are wrong but I don't know why. Could you please explain to me Reference Activity Duration (weeks) Predecessors Weeks activity can be
LS and LF are wrong but I don't know why. Could you please explain to me
| Reference | Activity | Duration (weeks) | Predecessors | Weeks activity can be crashed | Weekly cost of crash | ES | EF | LS | LF | Slack | | ||||||
| A | Hire workers | 8 | None | 3 | 2,000 | 0 | 8 | -4 | 4 | ||||||||
| B | Install equipment | 6 | None | 1 | 4,000 | 0 | 6 | -2 | 4 | ||||||||
| C | Order materials | 3 | None | 1 | 1,000 | 0 | 3 | 7 | 10 | ||||||||
| D | Test equipment | 4 | B | 2 | 2,500 | 6 | 10 | 6 | 10 | ||||||||
| E | Train workers | 6 | A,B | 2 | 5,000 | 8 | 14 | 4 | 10 | ||||||||
| F | Pilot Testing | 5 | C,D | 3 | 3,000 | 10 | 15 | 10 | 15 |