Question: Luis held a brainstorming session with his team. Since many of them are not familiar with MS Project, the team preferred to create the task

Luis held a brainstorming session with his team. Since many of them are not familiar with MS Project, the team preferred to create the task list and durations in Excel. In the Excel sheet, the columns are named Tasks and Estimated Durations. Luis' team does not know what summary tasks or milestone tasks are, so the list is quite raw. Which of the following options best describes how Luis should import the task list.

a) In the Excel sheet, select the area that contains the data. Do not include the Titles (Tasks and Estimated Durations).

b) Click Copy.

c)Navigate to a new blank project.

d) In the Table of the Gantt chart, click on the first cell below Task Name.

e) Click Paste.

f) Clean up the data by adding Summary tasks and milestone tasks, and indent the tasks appropriately.

a) In the Excel sheet, select the area that contains the data. Include the Titles (Tasks and Estimated Durations).

b) Click Copy.

c)Navigate to a new blank project.

d) In the Table of the Gantt chart, click on the first cell below Task Name.

e) Click Paste.

f) Clean up the data by adding Summary tasks and milestone tasks, and indent the tasks appropriately.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!