Question: Luis Sousa is the project manager for a construction project which is expected to finish in fourteen months. Luis would like to compare different sets
Luis Sousa is the project manager for a construction project which is expected to finish in fourteen months. Luis would like to compare different sets of baseline values every month on MS Project for this one plan. Which of the following would be the best approach? Question 19 options: Luis should change the default baseline every month. Luis should control task scheduling by using constraints. Luis should seek an alternate solution as MS Project is not capable of this feature. Luis should save multiple baselines (every month)