Question: LW 2 : Using Excel to automatically calculate performance measures Q1: For the jobs given below. First get the sequence of the jobs based on

LW 2 : Using Excel to automatically calculate performance measures Q1: For the jobs given below. First get the sequence of the jobs based on SPT. Next put the sequence and the respective process times and due dates in an excel table. Put in the correct formulae in each cell and automatically calculate the following: a. Average flow time b. Makespan c. Average tardiness d. Average lateness Job # Process Time 11 29 Due Date 61 1 2 45 3 31 31 4 33 1 2 5 32 Compare your answer with HW2 Q1. Example of Excel Model Start Time- 10 Proc Time Due Date Job Start End A 12 3 =SCSI =F4+C4 IC 4 17 =14 FE5+C5 Jobs Late Tardiness IF(G4