Question: M N O P Q R S T U V W Problem 5: A metal fabricating company has me rollowmg master production schedule for one


M N O P Q R S T U V W Problem 5: A metal fabricating company has me rollowmg master production schedule for one or Its Items (a frame), as well as the accompanying product structure, Week 1 Week 2 Week 3 Week 4 MP5 20 30 35 20 The resource prole for the frame is as follows: Item Work Center Setup Hours Run Hours/Unit Lead Time Frame 200 4 1'5 0 Week: Part A 300 3 1'0 1 week Part B 300 3 l8 1 week Part C 400 3 1 .2 2 weeks 23 Part D 500 3 1.0 1 week 24 25 Determine the capacity requirements for all work centers, assuming all usages are one, and that a new setup is 26 required in each week at each work centerl 27 28
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock