Question: Machine 0 Multiple Activity Chart (Man - Machine type) Time (in Sec.) Operation Man Man removes the rubber band. 3 Man Picks up weight from

Machine 0 Multiple Activity Chart (Man - Machine

Machine 0 Multiple Activity Chart (Man - Machine type) Time (in Sec.) Operation Man Man removes the rubber band. 3 Man Picks up weight from hopper. 5 Deck is placed in hopper. 7 Man replaces weight in deck. 9 Man Pushes start button 12 20 Man picks up deck from output stacker. 23 Rubber band is replaced on the deck Shown above is a case where a work task has been divided into work elements, which of the guidelines for defining the work elements in Direct Time Study has been breached here

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!