Question: Machine A 1 1 1 Machine B 1 hr move time 1 1 1 1 1 Sequence the jobs in priority order 1,2,3,4. Assume 8hr
| Machine A | 1 | 1 | 1 |
|
|
|
|
|
| |
| Machine B |
|
|
|
| 1 | 1 | 1 | 1 | 1 |
Sequence the jobs in priority order 1,2,3,4. Assume 8hr work days.
| Job | Work Center/Machine Hours | Due Date (Days) |
| 1 | A/3, B/2, C/2 | 3 |
| 2 | C/2, A/4 | 2 |
| 3 | B/6, A/1, C/3 | 4 |
| 4 | C/4, A/1, B/2 | 3 |
2. Problem 4
In problem 3, assume there are two machines of type A, two of type B, and two of type C.
Prepare a finite capacity schedule
How does your FCS compare to the performance of the Gantt chart in problem 2?