Question: Machine A 1 1 1 Machine B 1 hr move time 1 1 1 1 1 Sequence the jobs in priority order 1,2,3,4. Assume 8hr

Machine A

1

1

1

Machine B

1 hr move time

1

1

1

1

1

Sequence the jobs in priority order 1,2,3,4. Assume 8hr work days.

Job

Work Center/Machine Hours

Due Date (Days)

1

A/3, B/2, C/2

3

2

C/2, A/4

2

3

B/6, A/1, C/3

4

4

C/4, A/1, B/2

3

2. Problem 4

In problem 3, assume there are two machines of type A, two of type B, and two of type C.

Prepare a finite capacity schedule

How does your FCS compare to the performance of the Gantt chart in problem 2?