Question: Make a project management flowchart diagram showing the critical path Task Immidiate Predecesor Immidiate Successor Activity Duration A B 1 Hour B A C 1
Make a project management flowchart diagram showing the critical path
| Task | Immidiate Predecesor | Immidiate Successor | Activity Duration |
| A | B | 1 Hour | |
| B | A | C | 1 Hour |
| C | B | D, E | 1 Hour |
| D | C | K | 5 Hours |
| E | C | F | 7 Hours |
| F | E | K | 2 Days |
| G | B | H | 5 Hours |
| H | B | I | 2 Days |
| I | G,H | J | 3 Hours |
| J | G,H,I | K | 3 Hours |
| K | E,J | L | 5 Hours |
| L | K | M | 1 Hour |
| M | K, B, H | N | 1 Hour |
| N | M | O | 2 Days |
| O | N | P | 1 Day |
| P | O | 1 Day |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
