Question: Make it in AOA The activities needed to replace a broken window pane are given below. duration preceding activity (in mins) activities A A order

Make it in AOA
The activities needed to replace a broken window pane are given below. duration preceding activity (in mins) activities A A order glass 10 B collect glass 30 A remove broken pane 15 B, D D buy putty 20 E put putty in frame 3 put in new pane 2 E G putty outside and smooth 10 H sweep up broken glass 5 clean up 5 5 all (a) Construct an activity network. (b) What is the minimum time to complete the replacement? (c) What is the critical path? IT OmoStep by Step Solution