Question: Make sure you keep your Excel spreadsheet available because you may have questions using the same tree structure / BOM for different parts. Given the

Make sure you keep your Excel spreadsheet available because you may have questions using the same tree structure/BOM for different parts. Given the following information, develop a material requirements plan for end item A and its components. 50 and 80 units of A are needed at the beginning of week 6 and 8, respectively.
\table[[Item,On-Hand,On-Order,Lead Time],[A,20,-,1 wk],[B,-,-,2 wks],[C,60,-,1 wk],[D,150, Week 2),2 wks],[E,10,-,1 wk]]
B
C(2)
E (2)
The planned-order release for product A is:
Week 6: 50, Week 8: 80
Week 5: 50, Week 7: 80
Week 5:30, Week 7: 80
Week 6: 30, Week 8: 80
Week 5:30
MacBook Pro
 Make sure you keep your Excel spreadsheet available because you may

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!