Question: make WBS, work packages and activities for those work packages You are a Project Manager for Seneca Apps Inc. and you are making a project

You are a Project Manager for Seneca Apps Inc. and you are making a project budget to present it to the Senior Management Team. Use the following table and WBS template for this assignment: Activity 1 2 3 4 5 6 7 8 9 10 11 Unit Testing IPR Filing Connecting Software Project for Mrs. Y Requirement Collection Resource Allocation Hardware Specification Software Build Customized Connecting Software Preceding Activity None None 2 2 3 Task System Testing End to End Testing Project Handover END (Milestone) Requirement Collection Resource Allocation Customized Connecting Software Hardware and Software Built 4 3,9 6 5 7,9 10 Activity Time (Work Weeks) End of Testing 10 4 4 10 2 1 2 5 4 0 Project Handover