Question: MAKING A BURRITO Names: _________________________ TASKS Predecessor Task Time A Warm tortilla -none 20 sec B Rice -A 10 sec C Beans -B 10 sec

MAKING A BURRITO Names: _________________________

TASKS

Predecessor

Task Time

A

Warm tortilla

-none

20 sec

B

Rice

-A

10 sec

C

Beans

-B

10 sec

D

Meat

-B

10 sec

E

Salsa

-C, D

10 sec

F

Cheese

-E

5 sec

G

Sour Cream

-E

10 sec

H

Lettuce

-E

10 sec

I

Wrap

-F, G, H

15 sec

J

Bag

-I

5 sec

K

Checkout/pay

-J

25 sec

All the information needed to solve the following questions is given.

  1. Assign tasks to workstations:

  1. Efficiency of your burrito line:

  1. Actual output per hour:

  1. What if demand were such that 200 / hour were needed?

  1. What is the maximum # of burritos that can be produced in an hour with these specific times/tasks?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!