Question: Tasks Predecessor Task Time A Warm Tortilla None 20 Sec B Rice A 10 Sec C Beans B 10 sec D Meat B 10 sec
| Tasks | Predecessor | Task Time | |
| A | Warm Tortilla | None | 20 Sec |
| B | Rice | A | 10 Sec |
| C | Beans | B | 10 sec |
| D | Meat | B | 10 sec |
| E | Salsa | C,D | 10 sec |
| F | Cheese | E | 5 sec |
| G | Sour Cream | E | 10 sec |
| H | Lettuce | E | 10 sec |
| I | Wrap | F, G, H | 15 sec |
| J | Bag | I | 5 sec |
| K | Checkout | J | 25 sec |
Min CT: 25 MAX CT: 130
Cycle time: 36 minutes
Questions:
A. Assign Tasks to Workstations:
B. Efficiency of Burrito Line:
C. Actual Output per Hour:
D. What if demand were such that 200/ hour were needed?
E. What is the Maximum Number of Burritos that can be produced per hour?