Question: MAN 4 5 5 0 The project network along with normal and crash data are provided below. Crash the project network by 4 days. What
MAN
The project network along with normal and crash data are provided below. Crash the project network by days. What added cost is required to crash the project?
Note: Please show how you crashed the project ie which activities were crashed and by how many days they were crashed. Also provide the sequence in which the project was crashed
tableActivitytableNormalTime DaystableCrashTime DaysNormal Cost,tableCrashCosttableCrash Cost DayABCDEF
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
