Question: Management Information Systems What is the correct answer? 30. Which of the following is not an input to Plan Communications Management Process? a. Project charter

Management Information Systems What is the
Management Information Systems
What is the correct answer?
30. Which of the following is not an input to Plan Communications Management Process? a. Project charter b. Stakeholder Register and Stakeholder Management Plan c. Requirements Documentation d. Business Case and Benefits Management Plan