Question: Management is evaluating two mutually exclusive projects, X, and Y, with the following cash flows. Year End of year cash flows Project X Project Y
- Management is evaluating two mutually exclusive projects, X, and Y, with the following cash flows.
| Year | End of year cash flows | |
| Project X | Project Y | |
| 1 | -10,000 | -10,000 |
| 2 | 3,293 | 0 |
| 3 | 3,296 | 0 |
| 4 | 3,293 | 0 |
| 5 | 3,293 | 14,641 |
- If the required rate of return on both projects is 5%, which project should management choose? Why?
- If the required rate of return on both projects is 14%, which project should management choose? Why?
Step by Step Solution
3.49 Rating (159 Votes )
There are 3 Steps involved in it
Lets calculate the Net Present Value NPV of each project at both the 5 and 14 required rates of retu... View full answer