Question: manager needs to construct a material requirements plan. 200 units of product A and 100 units of product B need to be ready for delivery
manager needs to construct a material requirements plan. 200 units of product A and 100 units of product B need to be ready for delivery in week 6. 200 units of product B need to be available in week 7. Related information is gathered and listed in the following table. Item Lead Time (weeks) Amount on Hand Scheduled Receipts Lot Size Direct Components A 1 0 0 Lot-for-lot X(2), Z(2) B 1 20 0 Lot-for-lot X(2), Y X 1 100 0 Multiple of 250 Z(3) Y 2 0 60 (week 2) Multiple of 30 --- Z 2 300 600 (week 1) Multiple of 600 --- a) (20%) What are the planned order releases for each item (A, B, X, Y and Z)? b) (10%) What are the projected on hand inventory of each item at the end of week 8?