Question: Managers of a large construction company are using the program evaluation and review technique ( PERT ) to schedule, monitor, and control a project with

Managers of a large construction company are using the program evaluation and review technique (PERT) to schedule, monitor, and control a project with 25 activities. After creating the workflow structure and establishing the precedence relationships, the managers determined the critical path consists of 11 activities and calculated an expected project duration of 37 months and a project variance of 9 months.