Question: Manual simulation. In this exercise, you are asked to perform a manual simulation of one machine and 8 parts coming in for processing and wait
Manual simulation. In this exercise, you are asked to perform a manual simulation of one machine and 8 parts coming in for processing and wait in a single queue.The Arrival Time (Minutes) and Processing Time (Minutes) of the parts are given by the table below.
Table of Part Arrival and Processing Times:
| Customer | Arrival Time (Minutes) | Service Time (Minutes) |
| 1 | 0 | 4 |
| 2 | 8 | 1 |
| 3 | 14 | 4 |
| 4 | 15 | 3 |
| 5 | 23 | 2 |
| 6 | 26 | 4 |
| 7 | 34 | 5 |
| 8 | 41 | 4 |
- Simulate for 40 minutes and write down your simulation using the following template (Week 2, Page 66).
| Just-Finished Event | Variables | Attributes (Arrival Times) | Event Calendar | ||||||
| Entity No. | Time t | Event Type | Q(t) | B(t) | In Queue | In Service | Entity No. | Time | Type |
- Plot Q(t)and B(t) based on event changes (as shown in lecture notes)
- Calculate the following:
- Average waiting time of parts in queue
- Time-average number of parts in queue
- Average time in system for parts
- Average number of parts in system
- Utilization of the machine
- Total number of parts finished.
Step by Step Solution
There are 3 Steps involved in it
To simulate the operations of the machine and the queuing of parts as described well first conduct the manual simulation stepbystep keeping track of e... View full answer
Get step-by-step solutions from verified subject matter experts