Question: Many times project managers will be responsible for a project, yet the human resources assigned to the project do not report directly to the project
-
Many times project managers will be responsible for a project, yet the human resources assigned to the project do not report directly to the project manager. This is an example of:
a. Holacracy.
b. Matrix organization structure.
c. Authoritarian structure.
d. Managed organization structure.