Question: Marcella is faced with a big rush on her project due to a demand from the customer to bring the end - date in by

Marcella is faced with a big rush on her project due to a demand from the customer to bring the end-date in by 3 weeks. She decides to add 4 new coders and 10 testers to accelerate the timeline. Which form of schedule compression has Marcella applied?
Critical Path Merging
Fast-Tracking
Crashing
Escalation