Question: Gerta is faced with a big rush on her project due to a demand from the customer to bring the end-date in by 3 weeks.
Gerta is faced with "a big rush" on her project due to a demand from the customer to bring the end-date in by 3 weeks. She decides to do some testing in parallel that is usually, traditionally done in sequence. Gerta has chosen which form of schedule compression? a. Crashing b. Critical Path Merging c. Escalation d. Tracking