Question: Mark is a project manager analyzing earned value data on his project. He divides the budgeted cost of the remaining work by the current cost

Mark is a project manager analyzing earned value data on his project. He divides the budgeted cost of the remaining work by the current cost performance index, and then adds that amount to the costs already incurred on the project. Mark is calculating the?

Estimate at Completion (EAC)

Schedule Performance Index (SPI)

Cost Performance Index (CPI)

Budget at Completion (BAC)